Next important milestone successfully achieved – trial operation passed and takeover of operations by EnBW

Zu allen Neuigkeiten

As part of the modernization of the Stuttgart Münster waste-to-energy plant operated by EnBW, another key project phase in the conversion of the flue gas preheating system has been successfully completed.

EnBW Druckprobe 02

At the beginning of January 2026, EnBW officially declared the takeover of the first converted heat transfer system after successfully completing trial operation. This is a very good result for the overall project and a great conclusion to the first conversion phase.

We would like to express our special thanks to the entire team for their tireless dedication, high level of professionalism, and quick problem-solving skills.

Work on the two remaining heat exchange systems on lines 2 and 3 will begin as planned in April and August 2026. We are already looking forward to continuing our collaboration.

The success of this project impressively demonstrates that we combine technical expertise with sustainable solutions and integrate them reliably into complex existing structures.